A node was in the commissioning process and:

Stop bulk action did not stop the node.
Abort Commissioning bulk action did not stop the node.

Entered to the node page:

Abort Commissioning button did work.

It seems that bulk actions are still buggy.

Tags: papercut
Changed in maas:
status: New → Triaged
importance: Undecided → High
milestone: none → next
tags: added: papercut
Christian Reis (kiko)
Changed in maas:
milestone: next → 1.7.1
Revision history for this message
Raphaël Badin (rvb) wrote :

I just tried to reproduce this and I couldn't (using 1.7 rc1). I had two NUCs commissioning and using the bulk action "Abort commissioning" I managed to abort the commissioning process just fine.

Maybe it failed because you tried to abort the commissioning while the "power up" action initiated at the beginning of the commissioning phase was still running…? In which case you should have seen an error message similar to """The action "Abort commissioning" could not be performed on 2 nodes because their state does not allow that action."""

Revision history for this message
Raphaël Badin (rvb) wrote :

I tested again with what's in the 1.7 branch currently and I still cannot reproduce this. @Andres can you see if you can reproduce the problem and if you can, provide the steps to reproduce it?

Marking this as incomplete for now.

Changed in maas:
status: Triaged → Incomplete
Changed in maas:
milestone: 1.7.1 → 1.7.2
Changed in maas:
milestone: 1.7.2 → 1.7.3
Changed in maas:
status: Incomplete → Invalid
To post a comment you must log in.
This report contains Public information  
Everyone can see this information.

Other bug subscribers

Remote bug watches

Bug watches keep track of this bug in other bug trackers.