Bulk actions did not work while node was commissioning
Bug #1386482 reported by
Andres Rodriguez
This bug affects 1 person
Affects | Status | Importance | Assigned to | Milestone | |
---|---|---|---|---|---|
MAAS |
Invalid
|
High
|
Unassigned |
Bug Description
A node was in the commissioning process and:
Stop bulk action did not stop the node.
Abort Commissioning bulk action did not stop the node.
Entered to the node page:
Abort Commissioning button did work.
It seems that bulk actions are still buggy.
Changed in maas: | |
status: | New → Triaged |
importance: | Undecided → High |
milestone: | none → next |
tags: | added: papercut |
Changed in maas: | |
milestone: | next → 1.7.1 |
Changed in maas: | |
milestone: | 1.7.1 → 1.7.2 |
Changed in maas: | |
milestone: | 1.7.2 → 1.7.3 |
Changed in maas: | |
status: | Incomplete → Invalid |
To post a comment you must log in.
I just tried to reproduce this and I couldn't (using 1.7 rc1). I had two NUCs commissioning and using the bulk action "Abort commissioning" I managed to abort the commissioning process just fine.
Maybe it failed because you tried to abort the commissioning while the "power up" action initiated at the beginning of the commissioning phase was still running…? In which case you should have seen an error message similar to """The action "Abort commissioning" could not be performed on 2 nodes because their state does not allow that action."""