Dependency lag days does not respect the calendar
Affects | Status | Importance | Assigned to | Milestone | |
---|---|---|---|---|---|
planner |
New
|
Medium
|
|||
planner (Ubuntu) |
New
|
Undecided
|
Unassigned |
Bug Description
The dependency lag should take into account the default calendar and do not count the weekend days as lag days.
Easier to see in an example:
You have 2 tasks of 1d work and mark a dependency from A to B with a lag of 3 days.
A -> B (3 days)
The wrong plannig says:
Planning (Project starts on Thursday):
Thu: A
Fri: -
Sat: - (weekend)
Sun: - (weekend)
Mon: B
The plannig should say:
Thu: A
Fri: -
Sat: - (weekend)
Sun: - (weekend)
Mon: -
Tue: -
Wed: B
Extra info:
$ lsb_release -rd
Description: Ubuntu 12.04.1 LTS
Release: 12.04
$ apt-cache policy planner
planner:
Installed: 0.14.5-1ubuntu3
Candidate: 0.14.5-1ubuntu3
Version table:
*** 0.14.5-1ubuntu3 0
500 http://
100 /var/lib/
Changed in planner: | |
importance: | Unknown → Medium |
status: | Unknown → New |
This is not the right place to report this. Please file it at https:/ /bugzilla. gnome.org/ enter_bug. cgi?product= planner